taskAdvanced Gtk+ Sequencer - Tasks: task #14177, Implement AgsServer and related...

 
 

You are not allowed to post comments on this tracker with your current authentication level.

task #14177: Implement AgsServer and related controllers

Submitter:  Joël Krähemann <jkraehemann>
Submitted:  Wed 12 Oct 2016 06:32:01 AM UTC
   
 
Should Start On:  Tue 11 Oct 2016 10:00:00 PM UTC Should be Finished on:  Wed 06 May 2020 10:00:00 PM UTC
Category:  version 3.0.x Priority:  5 - Normal
Status:  Done Privacy:  Public
Assigned to:  jkraehemann Percent Complete:  100%
Open/Closed:  Closed Effort:  0.00

Jump to the original submission

Sun 08 Dec 2019 08:43:07 AM UTC, comment #6: 

added unit-tests.

Joël Krähemann <jkraehemann>
Group administrator
Sat 07 Dec 2019 06:18:36 PM UTC, comment #5: 

added test skelletons

Joël Krähemann <jkraehemann>
Group administrator
Sat 07 Dec 2019 08:28:47 AM UTC, comment #4: 
  • implemented AgsFrontController
  • implemented AgsPluginController


Joël Krähemann <jkraehemann>
Group administrator
Fri 06 Dec 2019 07:55:54 AM UTC, comment #3: 
  • implemented AgsXmlPasswordStore


Joël Krähemann <jkraehemann>
Group administrator
Fri 06 Dec 2019 07:14:26 AM UTC, comment #2: 
  • implemented AgsXmlAuthentication


Joël Krähemann <jkraehemann>
Group administrator
Thu 05 Dec 2019 02:09:39 PM UTC, comment #1: 

implemented:

  • ags_authentication_manager_login()
  • ags_authentication_manager_logout()


... and related:

  • ags_xml_authentication_login()
  • ags_xml_authentication_logout()


... and AgsLoginInfo.

Joël Krähemann <jkraehemann>
Group administrator
Wed 12 Oct 2016 06:32:01 AM UTC, original submission:  

The AgsServer is a XML-RPC server to do remote control of Advanced Gtk+ Sequencer.

You should implement basic authentication and the ability to do client certificate verification. The controllers should communicate with the application.

Joël Krähemann <jkraehemann>
Group administrator

 

(Note: upload size limit is set to 16384 kB, after insertion of the required escape characters.)

No files currently attached

 

Depends on the following items: None found

Items that depend on this one: None found

 

Carbon-Copy List
  • -email is unavailable- added by jkraehemann (Submitted the item)
  •  

    There are 0 votes so far. Votes easily highlight which items people would like to see resolved in priority, independently of the priority of the item set by tracker managers.

     

    Follow 13 latest changes.

    Date Changed by Updated Field Previous Value => Replaced by
    2019-12-08 jkraehemann Open/ClosedOpen Closed
    2019-12-08 jkraehemann StatusReady For Test Done
    2019-12-07 jkraehemann StatusIn Progress Ready For Test
    2019-12-07 jkraehemann Percent Complete50% 100%
    2019-12-06 jkraehemann Percent Complete20% 50%
    2019-12-05 jkraehemann Should be Finished on2016-11-30 2020-05-06
        CategoryNone version 3.0.x
        StatusPostponed In Progress
        Percent Complete0% 20%
    2019-12-03 jkraehemann StatusIn Progress Postponed
    2016-12-06 jkraehemann StatusNone In Progress
        Assigned toNone jkraehemann
    2016-10-12 jkraehemann Should be Finished on2016-10-30 2016-11-30

    Back to the top

    Powered by Savane 3.13-4448.