task #3651: Implementation of GXS

Submitter:  Simon Foster <repton>
Submitted:  Mon 17 Jan 2005 04:12:29 PM UTC
   
 
Should Start On:  Mon 17 Jan 2005 12:00:00 AM UTC Should be Finished on:  Sat 05 Feb 2005 12:00:00 AM UTC
Category:  None Priority:  9 - Immediate
Status:  None Privacy:  Public
Assigned to:  repton Percent Complete:  100%
Open/Closed:  Closed Effort:  3.00

Sat 05 Feb 2005 09:30:13 PM UTC, comment #2: 

GXS is now in a state suitable for most things we will require to do in this project. It is not complete, and will probably be expanded as needs must through the project, but the most essential features work. Including the de/serialization of SOAP Envelopes.

Simon Foster <repton>
Group administrator
Tue 01 Feb 2005 06:38:12 PM UTC, comment #1: 

We've somewhat come to a halt on this, while trying to uncover the source of a nasty bug which sends the dictionary lookup for the XMLNamespace type-classe into an infinite loop.

Simon Foster <repton>
Group administrator
Mon 17 Jan 2005 04:12:29 PM UTC, original submission:  

The completion of the new modular version of GXS is paramount to the engine side. Currently a working serializer is present, and the deserializer is the next priority.

Simon Foster <repton>
Group administrator

 

(Note: upload size limit is set to 16384 kB, after insertion of the required escape characters.)

No files currently attached

 

Depends on the following items: None found

Digest:
   task dependencies.

 

CC list is empty

 

There are 0 votes so far. Votes easily highlight which items people would like to see resolved in priority, independently of the priority of the item set by tracker managers.

 

Follow 8 latest changes.

Date Changed by Updated Field Previous Value => Replaced by
2005-02-05 repton Percent Complete80% 100%
    Open/ClosedOpen Closed
2005-02-01 repton Dependencies- task #3655 is dependent
2005-02-01 repton Should be Finished on2005-01-28 2005-02-05
    Percent Complete50% 80%
    Effort0.00 3.00
2005-01-17 repton Priority1 - Later 9 - Immediate
2005-01-17 repton Dependencies- task #3653 is dependent