task #10708: Improve complex script rendering module

Submitter:  Santhosh Thottingal <santhosh>
Submitted:  Wed 20 Oct 2010 04:56:17 PM UTC
   
 
Should Start On:  Tue 19 Oct 2010 06:30:00 PM UTC Should be Finished on:  Fri 19 Nov 2010 06:30:00 PM UTC
Category:  None Priority:  7 - High
Status:  In Progress Privacy:  Public
Assigned to:  vasudev Percent Complete:  100%
Open/Closed:  Closed Effort:  0.00

Sat 13 Nov 2010 09:07:25 AM UTC, comment #2: 

Font color support is added. I'm having trouble while adding font_size when I add this support something goes wrong I'm still investigating. Apache process doubles all of a sudden with no response comming back. Similarly request will be processed forever in stand alone version pressing Ctrl-C shows the module is stuck in guessLanguage module.

Vasudev Kamath <vasudev>
Group Member
Sun 07 Nov 2010 04:55:33 AM UTC, comment #1: 

We just added support for SVG, PNG, PDF formats. There are  few isues, but the basic rendering works fine.
http://silpa.smc.org.in/Render

Font, color etc are not configurable now.

Santhosh Thottingal <santhosh>
Group administrator
Wed 20 Oct 2010 04:56:17 PM UTC, original submission:  

Server side complex script rendering module : http://silpa.smc.org.in/Render

This should have option for PNG, SVG, PDF output support.
Font, size, color should be selectable.
Margin should be configurable.

Santhosh Thottingal <santhosh>
Group administrator

 

(Note: upload size limit is set to 16384 kB, after insertion of the required escape characters.)

No files currently attached

 

Depends on the following items: None found

Items that depend on this one: None found

 

Carbon-Copy List
  • -email is unavailable- added by vasudev (Posted a comment)
  • -email is unavailable- added by santhosh (Submitted the item)
  •  

    There are 0 votes so far. Votes easily highlight which items people would like to see resolved in priority, independently of the priority of the item set by tracker managers.

     

    Follow 7 latest changes.

    Date Changed by Updated Field Previous Value => Replaced by
    2010-12-31 vasudev Percent Complete70% 100%
        Open/ClosedOpen Closed
    2010-11-13 vasudev Priority5 - Normal 7 - High
        Percent Complete50% 70%
    2010-11-07 santhosh StatusNone In Progress
        Percent Complete0% 50%
        Assigned toNone vasudev