taskSwathanthra Malayalam Computing - Tasks: task #9058, debian lenny release notes...

 
 
Show feedback again

You are not allowed to post comments on this tracker with your current authentification level.

task #9058: debian lenny release notes Malayalam translation

Submitted by:  Praveen A <praveen_a>
Submitted on:  Tue 27 Jan 2009 08:57:38 AM UTC  
 
Category: translationShould Start On: Mon 26 Jan 2009 06:30:00 PM UTC
Should be Finished on: Thu 12 Feb 2009 06:30:00 PM UTCPriority: 9 - Immediate
Status: In ProgressPrivacy: Public
Percent Complete: 80%Assigned to: SMC Localization Team <smc-localization>
Open/Closed: OpenEffort: 0.00

Fri 13 Feb 2009 11:45:01 PM UTC, comment #4:

It was deactivated (when we did not complete 80%), but my request to add it is accepted (now we have 82%). I have also requested to use ttf-malayalam-fonts from lenny for building pdf. Lets see how it goes.

Praveen A <praveen_a>
Project Administrator
Fri 13 Feb 2009 07:06:33 AM UTC, comment #3:

http://download.savannah.gnu.org/releases-noredirect/smc/debian/release-notes.all.html/statistics.html

We crossed 70, now all languages that have a translation is above us.

Praveen A <praveen_a>
Project Administrator
Tue 10 Feb 2009 09:16:23 PM UTC, comment #2:

3 more days left

Can we make ml green at
http://www.debian.org/releases/testing/statistics.html ?

Praveen A <praveen_a>
Project Administrator
Thu 05 Feb 2009 08:59:58 PM UTC, comment #1:

http://www.debian.org/releases/testing/i386/release-notes/index.ml.html

Praveen A <praveen_a>
Project Administrator
Tue 27 Jan 2009 08:57:38 AM UTC, original submission:

More details on how to join

http://wiki.smc.org.in/index.php?title=ഡെബിയന്‍_മലയാളം/പ്രസാധനക്കുറിപ്പുകളുടെ_മലയാളം_പരിഭാഷ

We have barely a week to complete it before lenny is out.

Praveen A <praveen_a>
Project Administrator

 

No files currently attached

 

Depends on the following items: None found

Items that depend on this one: None found

 

Carbon-Copy List
  • -unavailable- added by praveen_a (Submitted the item)
  •  

    Do you think this task is very important?
    If so, you can click here to add your encouragement to it.
    This task has 0 encouragements so far.

    Only logged-in users can vote.

     

    Please enter 421 here (basic anti-spam test):

     

     

    Follow 5 latest changes.

    Date Changed By Updated Field Previous Value => Replaced By
    Fri 13 Feb 2009 11:45:01 PM UTCpraveen_aPercent Complete70%=>80%
    Fri 13 Feb 2009 07:06:32 AM UTCpraveen_aPercent Complete60%=>70%
    Tue 10 Feb 2009 09:16:23 PM UTCpraveen_aShould be Finished onMon 26 Jan 2009 06:30:00 PM UTC=>Thu 12 Feb 2009 06:30:00 PM UTC
      Percent Complete50%=>60%
    Thu 05 Feb 2009 08:59:58 PM UTCpraveen_aPercent Complete10%=>50%
    Show feedback again

    Back to the top


    Powered by Savane 3.1-cleanup