taskMapOSMatic - Tasks: task #9691, Add an RSS feed for /maps/ page

 
 

task #9691: Add an RSS feed for /maps/ page

Submitter:  David MentrĂ© <dmentre>
Submitted:  Thu 10 Sep 2009 03:20:05 PM UTC
   
 
Should Start On:  Wed 09 Sep 2009 10:00:00 PM UTC Should be Finished on:  Sun 07 Feb 2010 11:00:00 PM UTC
Category:  web Priority:  * 4
Status:  Done Privacy:  Public
Assigned to:  mpetazzoni Percent Complete:  100%
Open/Closed:  Closed Release:  None
Effort:  0.00
* Mandatory Fields

Add a New Comment Rich Markup
   

Wed 17 Feb 2010 11:59:20 AM UTC, comment #2: 

This is in production (deploy-20100212).

Maxime Petazzoni <mpetazzoni>
Group administrator
Wed 10 Feb 2010 03:32:02 PM UTC, comment #1: 

Feed is available for test at http://dev.maposmatic.org/feeds/maps/

Maxime Petazzoni <mpetazzoni>
Group administrator
Thu 10 Sep 2009 03:20:05 PM UTC, original submission:  

Add an RSS feed for /maps/ page, globally accessible from any page of the web site.

David Mentré <dmentre>
Group administrator

 

(Note: upload size limit is set to 16384 kB, after insertion of the required escape characters.)

Attach Files:
   
   
Comment:
   

No files currently attached

 

Depends on the following items: None found

Items that depend on this one: None found

 

Carbon-Copy List
  • -email is unavailable- added by mpetazzoni (Updated the item)
  • -email is unavailable- added by dmentre (Submitted the item)
  •  

    There are 0 votes so far. Votes easily highlight which items people would like to see resolved in priority, independently of the priority of the item set by tracker managers.

    Only logged-in users can vote.

     

    Follow 13 latest changes.

    Date Changed by Updated Field Previous Value => Replaced by
    2010-02-17 mpetazzoni StatusReady For Test Done
        Percent Complete90% 100%
        Open/ClosedOpen Closed
    2010-02-10 mpetazzoni StatusPatch exists Ready For Test
    2010-02-09 mpetazzoni Priority5 - Normal 4
        StatusReady For Test Patch exists
    2010-02-04 mpetazzoni StatusIn Progress Ready For Test
        Percent Complete70% 90%
    2010-02-04 mpetazzoni Should be Finished on2009-09-09 2010-02-07
        CategoryNone web
        StatusNone In Progress
        Percent Complete0% 70%
        Assigned toNone mpetazzoni